PROGRESS ON UINTAH VIEW
Progress on Uintah View is a little behind schedule due to rock and ledge. Crews were unable to lay pipe for about 4 days due to this rock, we had to jackhammer in order to continue. The pipe is now down around the sharp corner about half way down and will continue as planned.
Read MorePROGRESS ON NAVAJO RD.
Our progress on Navajo Rd. is on schedule as planned, the crews are on there way up Deer Loop this week (8/22/06) and should have it completed by the end of this week (8/25/2006). Once Deer Loop is completed the crew will head down Navajo and then up Yellow Moon when they reach that intersection,…