Posts by Manager
ALEXANDER CANYON CONSTRUCTION TO BEGIN 8/20/07
We will begin construction on Alexander Canyon on August 20 2007. We will be starting from the west end at the intersection of Uintah View and Alexander so please make sure your tanks are full if you have them. We will be putting in valves every 1500 feet to allow us to turn the water…
Read MoreUNCLE TOMS WELL DOWN
Uncle Toms well went down on Saturday morning, since this well is our main producer please be aware that some areas are going to run out of water. This well pump is 620 feet in the ground and must be pulled out to be changed, we have contacted numorous pump companies and the soonest we…
Read MoreLEAK ON FOREST MEADOW ROAD AND GRAND VIEW
We still have a leak on the south side of FMR and Grand View Lane. Crews have been digging in this area and have not been able to find it. We have a leak detector coming up next week to see if he can narrow the search down. If the tanks start to drop rapidly…
Read MoreWOODCHUCK WAY OFF
Crews have made it to the top of the hill so we had to shut the water off so they can keep laying pipe. They will go past Woodchuck Way to get to the 2ook tank first, then back down to Woodchuck. Thank you for your patience regarding this matter.
Read MoreNAVAJO DRIVE IS GOOD TO DRINK
We have been flushing the line and got a bacteria sample back and it is good to drink the water now. Thank you for your patience regarding this matter.
Read MoreFOREST MEADOW BACK ON
We fixed the leak on the Forest Meadow side and the water is back on.
Read MoreFOREST MEADOWS OFF DUE TO LEAK
We had a main line break on Arapahoe and due to power lines right on top of the main line we could not get a bluestake till late Tuesday afternoon. Once we recieved clearance to dig the crews got the line dug and ready to go. We did not have one part we needed so…
Read MorePLEASE BE ON THE LOOK OUT FOR A LEAK
We have lost a lot of water over the last week in a half and have been unable to find a leak in the mains, we are hoping someone did not leave there meter on and it is filling a basement or watering the ground outside. Please check your meter to see if you have…
Read MoreELK RD. CONSTRUCTION BEGINS ON JUNE 11th
We will be shutting the line down on Elk Rd. June 11th around the morning time. Crews will begin at the intersection of Elk Rd. and Aspen View. You will always have access to your property, unless we are digging past it on that day, but we will backfill so you have access to your…
Read MoreASPEN VIEW CONSTRUCTION BEGINS
We have begun construction on Aspen View, we decided to start this line because it was still frozen and we still had over 2,000 ft of pipe broke. We made this decision based on what it would cost us to repair the line or just start laying new line and get it done. The crew…
Read More