METER READINGS

We started to read meters on 10/9/06 if your meter was left on the water manager shut it off.  If you do not have water to your lot please check to see if your meter is on before contacting the water company.

Read More

ATTENTION ALL RESIDENTS ON RUNNING DEER CIRCLE

We are asking all residents on Running Deer Circle to please have your vehicle out by 8:30 A.M. due to road construction being done on that road.  The road will be re-opened at 5:30 P.M. and you will be able to drive in. Thank You.

Read More

TRAFFIC ON NAVAJO & RUNNING DEER LOOP

All traffic on Navajo Rd. & Running Deer must come in from the top at the intersection of Navajo & Uintah View.  There will be no through traffic from the intersection of Pine Meadow Drive and Navajo until the 9th or 10th of October.  Thank You

Read More

UPDATE ON NAVAJO RD.

Crews are within 200 ft from the intersection of Navajo Rd. and Running Deer Circle they will complete the Navajo line and then begin up Running Deer Circle.  There is no through traffic on Navajo until crews go up Running Deer.

Read More

WORK STARTING ON MODOC LOOP & SALT BOX CIRCLE

Work will begin on these two roads 9/28/2006 and should not take very long to complete.  Crews will start at the intersection of Tollgate Canyon Rd. and go down The road to Salt Box Circle.

Read More

UINTAH VIEW COMPLETE

We have got all water restored to Uintah View Rd. and Alexander Canyon.  All the pipe line is laid, but there is still minor things to do such as haul off dirt piles and clean up.  Please be polite to all crews working on the water project.  Thank You PMMW Manager

Read More

UPDATE ON NAVAJO RD, DEER LOOP & YELLOW MOON

Navajo Rd. has now been turned on down to the intersection of Navajo Rd. and Yellow Moon.  This completes Navajo down to Yellow Moon including Deer Loop, all water has been flushed and if you have a new meter you may turn your water on.  If you do not have a new meter the meter crew will…

Read More

UPDATE ON UINTAH VIEW

Crews on Uintah View have got all meters tied back in and water will be restored to those meters by 8/31/2006.  The rest of the pipe line we are hoping to have done by the second week of September,  as long as the digging goes as planned.

Read More

UPDATE ON NAVAJO RD.

The crews on Navajo Rd. have completed Deer Loop and are now down to the intersection of Navajo and Yellow Moon.  Digging has gone a little slower due to hard sand stone, but we are still making progress.  Water will be restored down to and up Deer Loop possibly by the 8th of Sept. and…

Read More

PROGRESS ON UINTAH VIEW

Progress on Uintah View is a little behind schedule due to rock and ledge.  Crews were unable to lay pipe for about 4 days due to this rock, we had to jackhammer in order to continue.  The pipe is now down around the sharp corner about half way down and will continue as planned.

Read More