UPDATE ON UINTAH VIEW
Crews on Uintah View have got all meters tied back in and water will be restored to those meters by 8/31/2006. The rest of the pipe line we are hoping to have done by the second week of September, as long as the digging goes as planned.
Read MoreUPDATE ON NAVAJO RD.
The crews on Navajo Rd. have completed Deer Loop and are now down to the intersection of Navajo and Yellow Moon. Digging has gone a little slower due to hard sand stone, but we are still making progress. Water will be restored down to and up Deer Loop possibly by the 8th of Sept. and…
Read MorePROGRESS ON UINTAH VIEW
Progress on Uintah View is a little behind schedule due to rock and ledge. Crews were unable to lay pipe for about 4 days due to this rock, we had to jackhammer in order to continue. The pipe is now down around the sharp corner about half way down and will continue as planned.
Read MorePROGRESS ON NAVAJO RD.
Our progress on Navajo Rd. is on schedule as planned, the crews are on there way up Deer Loop this week (8/22/06) and should have it completed by the end of this week (8/25/2006). Once Deer Loop is completed the crew will head down Navajo and then up Yellow Moon when they reach that intersection,…