ELK RD. CONSTRUCTION BEGINS ON JUNE 11th

We will be shutting the line down on Elk Rd. June 11th around the morning time. Crews will begin at the intersection of Elk Rd. and Aspen View. You will always have access to your property, unless we are digging past it on that day, but we will backfill so you have access to your…

Read More

ASPEN VIEW CONSTRUCTION BEGINS

We have begun construction on Aspen View, we decided to start this line because it was still frozen and we still had over 2,000 ft of pipe broke. We made this decision based on what it would cost us to repair the line or just start laying new line and get it done. The crew…

Read More

NAVAJO DRIVE UPDATE

Navajo Drive is almost done, we have turned the water on halfway up and we are hoping to have it done by Tuesday June 12. We will have all meters tied in and we will just have to flush the line. Thank you for your patience with this matter.

Read More